Cadence Minerals completes capex scheme, finds $63.2 million savings

Archived article

Please note that tax, investment, pension and ISA rules can change and the information and any views contained in this article may now be inaccurate.

Cadence Minerals PLC announced on Friday the successful completion of a capital expenditure optimisation programme at its Amapa project in Brazil, alongside identifying $63.2 million in cost savings.

The London-based mineral resource investor has invested approximately $12.1 million into the project with an equity stake standing at 32.6%. The iron ore project consists of a mine, processing plant, wholly owned port and a 194 kilometre railway.

In 2023, Pedra & Branca Alliance Pte Ltd, the owners of the project, employed an engineering firm to conduct an in-depth review of the processing plant with the aim of reducing capital and operating expenditures, and possibly improving iron ore concentrate quality.

Cadence Chief Executive Officer Kiran Morzaria said: ‘We’re thrilled to announce the successful completion of our capital expenditure optimisation program at the Amapa iron ore project. This effort has delivered a substantial 33% reduction in capital costs, saving $63.2 million and forecasted a 4.8% to 5.5 Mtpa increase in iron ore concentrate production.’

Following the study Cadence & PBA have decided to redesign the mine to facilitate cost reductions.

Shares in Cadence Minerals were up 12% to 5.71 pence in London on Friday morning.